About RAMPCO     |     Our Operations
 
 EPC Contract of Tabriz Urmia Pipeline

In 2012, Iranian Oil Company has defined a plan to supply required fuel and energy for North West of Iran by a pipeline to reduce its transportation expenses. This pipeline starts from Tabriz refinery and ends in Urmia city of Iran with total length of 273 km. It includes a 14» Pipeline and a branch with size of 10» to Khoy.


The onus on the RAMPCO to execute Design, Procurement, Construction, Testing and Commissioning of Tabriz-Urmia pipeline. Including all civil, Mechanical and Corrosion protection activities with total length of 222 km, 14” and for 34 km, 10” and for 17 km, 8” .

For download Tabriz-Urmia Pipeline Project`s Brochure Click HERE

 

Contact              Work with RAMPCO

All Rights reserved © RampcoGroup