1992

  • The idea of establishing the Company was conceived by its founders and this vision came to being in 1992. The company received its first big overhaul project from Razi Petrochemical Company.
1993

The contract for reconstruction of Imam Khomeini Petrochemical Complex was concluded with the use of 3.500 direct personnel.

1995

Chlor_Alkali Unit of Bandar Imam Petrochemical Complex was established along with the Conclusion of the first construction contract for Cooling Tower with the participation of a German company for the PVC unit of Bandar Imam Petrochemical Complex.

1996
1996

1996

Design and Implementation of a CMMS System for the First Time in the Country

1999
1999

1999

Establishment of the First Private-Sector Human Resources Training Center for the Petrochemical Industry

First-Ever Manufacturing of Spiral Gaskets in the Country

 

2001

The first furnace unit for Abadan Petrochemical Plant was manufactured.

2005

Rampco’s First EPCF contract for Mehr Petrochemical project and EPC contact for the Oil and Gas sector of Mahshar-Abadan Pipeline were secured along with its first “West Ethylene Pipeline “with The length of 200 km.

2007

  • Upon signing the contract for manufacturing boilers & water supply in Mehr Petrochemical Project the Water and Energy sector of Rampco emerged and developed.
2008
2008 – Kavian

2008 – Kavian

The Construction Contract for the Olefin Unit of the Kavian Petrochemical Complex was awarded, making it the largest unit of its kind ever constructed. Rampco also acquired a 60% stake from the Petrochemical Investment Company and became a privately held company.

2011

Establishing the Koushan Charity Foundation and introducing it as the shareholder of the 30% of RAMPCO’ Stock Share was a major step towards fulfilling its social responsibilities.

2012

Conclusion of the EPC contract of Sulfuric Acid production plant was a starting point in the Mineral processing

2013

By the joint implantation of major overhaul projects of Sohar Refinery in Oman, Rampco entered the international market.

2017

The Separation of Ownership and Management in the company took shape and also, Rampco Entered O&M project implementation

2018
2018

2018

Design, Procurement, Construction & Installation of the Dareh-Zar Copper Flotation Concentration Plant

2020
2020 – Bandar Abbas

2020 – Bandar Abbas

Bandar Abbas, Rafsanjan & Sirjan Pump Stations and Terminals